Week 9
Week 8
During the 8th week, we worked on designing our new bridge that has to span 3 feet. We tried a few different side designs to see which one we felt most comfortable with. We built the bridge based on the design we thought was the best in terms of its weight holding capacity (as predicted) and the price. We then tested the bridge using the parameters we will be using in the next week for the official testing of the bridges. It was able to hold decent amount of weight on the first try (about 25 lbs) so we decided to reduce its cost by removing some of the members connecting the two sides of the bridge. We tested it again but the amount of weight it held dropped significantly. So our plan for next week is to re-design the final bridge that can hold decent amount of weight without failing which we will be test during week 9. The only accomplishment this week was to test the same design with different number of members connecting the two sides of the bridge which gave us an idea on how much the connecting pieces contribute to its weight holding capacity.
Week 7
Week 6
Week 5
Week 4
Week 3
Week 1
During the first week of ENGR-103, most of the class time was taken to explain the course goals and objectives. In the remaining time we divided into groups of 3 people who will be working as a team for the bridge design module. We introduced ourselves to each other, exchanged contact information and filled out the group information sheet. In the coming week, we plan to conduct some research on different types of bridges so we can enhance our knowledge and incorporate those ideas in our own bridge design. For example we can see how an arc shape can be integrated with a truss design. Our major accomplishment from week 1 is the setup of our blog which is a major component for this course. There aren’t any major issues that we face at this point since it has only been one week and we haven’t gotten deep into the project components yet. The first week’s reading focuses on teamwork which is not only a part of this course, but almost all the engineering fields. With multiple people in a group, there may be a few problems that may arise in the future. For example, not everyone’s thoughts and opinions are always going to be the same when making a decision. In which case, we plan to give everyone a chance to explain their opinion and listen to them from their point of view, and then make our decision based on the facts presented. One of the other problems might come up when deciding on a group meeting time. Since everyone would have different schedules, and me being a commuter, it would be hard to decide on a time that is convenient for everyone. In that case we would have to compromise and work our way around the busy schedule.
During week 9 we tested the final 3 foot bridge that we
designed as a team, and spent the rest of the time in taking apart the bridge
parts and returning them to their appropriate containers. We also briefly
looked over the deliverables for A4 in case we had any questions about it. The
major accomplishment was that we successfully finished the bridge module
without any issues. During the next week we will be working on A4 which will be
the last assignment for this class. We did not have any major issues throughout
the term.
Looking back at the bridge module, I learned a lot from each
of the goals identified in the course description. Teamwork was almost integrated
throughout this course. Each of the bridge projects helped me learn the process
of planning, documenting, design process by which the design undergoes modifications,
computer modeling and physical modeling. I also learned forensic analysis
through the actual testing of the Knex bridges. Static analysis gave us the
basic knowledge on how to calculate forces on individual members which would be
similar to any large scale bridge projects. To accomplish all these tasks, we
used a variety of software that I had never used before, but certainly gained
efficiency in using them upon finishing this term.
All the goals taught
something to us, but based on the area of engineering I am planning on
concentrating, the bridge analysis was the least beneficial for me. The
specific analysis of the bridge did not serve much help, but the overall idea
of analyzing something in detail would certainly apply to most of the engineering
disciplines. The most beneficial aspect of this course was the teamwork and
design process. Again, those two things are something that applies to all the
engineering fields. They taught me how to work efficiently with others, and how
to make changes to a product while designing it. For future, I would substitute
one of the Knex bridge assignments (2 feet or 3 feet) with something different.
Week 8
During the 8th week, we worked on designing our new bridge that has to span 3 feet. We tried a few different side designs to see which one we felt most comfortable with. We built the bridge based on the design we thought was the best in terms of its weight holding capacity (as predicted) and the price. We then tested the bridge using the parameters we will be using in the next week for the official testing of the bridges. It was able to hold decent amount of weight on the first try (about 25 lbs) so we decided to reduce its cost by removing some of the members connecting the two sides of the bridge. We tested it again but the amount of weight it held dropped significantly. So our plan for next week is to re-design the final bridge that can hold decent amount of weight without failing which we will be test during week 9. The only accomplishment this week was to test the same design with different number of members connecting the two sides of the bridge which gave us an idea on how much the connecting pieces contribute to its weight holding capacity.
We have completed almost 9 weeks of the bridge module which
has brought many new things into my perspective. I learned quite a few things from
the bridge design tools such as WPBD, Knex, truss analysis etc. that we
utilized throughout the term. One of techniques I learned in designing a bridge
when our goal is to have the lowest cost is that you can analyze the
compression and tension forces using WPBD and try to reach the ratio of 1. This
can be done by using different variations throughout the bridge which include
changing the member size, material and length etc. while reaching a ‘functioning’
bridge. However, in real world, the bridge would be undergoing a lot of
external forces such as wind turbulence etc. The amount of force applied by the
vehicles travelling over the bridge would also vary constantly. So to ensure
the safety, the bridge would have to be designed such that it can withstand the
maximum amount of force. Every members and gusset plates would have to be
analyzed in great detail to ensure that they wouldn’t give up under the normally
expected force. In this case, the safety would be the first priority, not the
overall cost of the bridge.
Week 7
During week 7, we briefly looked through the assignment 3 deliverables
which asks us to perform a simple truss analysis on a 7 member bridge. We also
browsed through the accompanying video which showed us how to perform the
calculation to make sure we understand everything so we can ask questions to TA
if something was unclear. Our group planned on doing the actual assignment
outside of class in an environment where we could hear the sound of the video
better without disturbing others around us. We then spent the remaining period
of the class in brainstorming ideas for our next bridge. A major accomplishment
for this week would be analysis of the sample bridge as well as our own bridge
using the Bridge Designer software. While Knex does not provide us with box
answers for the tension and compression forces, this method certainly helped us
by giving us some ideas about the forces acting on the members of our bridge.
Using Bridge Designer software for the analysis only gives
us a rough idea about the forces acting on the bridge. These forces are
calculated without taking into account the weights of the members. While in
real world, the weight of the members would play a crucial role. The force of
the load is directly applied at a single point (center) in the Bridge Designer,
while in real world the forces caused by the live load would be under constant
change as vehicles move across the bridge. In real world, external forces such
as wind affect the total forces acting on the bridge, which is not a parameter for
Bridge Designer. As far as the Knex bridge is concerned, it would be helpful to
know the magnitude of forces that cause the joints of the members to the gusset
plates break.
For the coming week we plan to analyze the Bridge Designer
results in order to help navigate our design process in making a strong and
cost efficient bridge.
Week 6
Major portion of this week’s class was used in
testing the bridge designed by our group during last week. We made some final
adjustments to our design by changing the gusset plate connections at a few of
the joints. The test parameters included a 2 feet span where the bridge would
be suspended with a bucket hanging from the center. The weight was added in the
form of sand which allowed us to get an accurate weight at which the bridge failed.
Our bridge, which cost us $124,000 held 24.8 lb, resulting in a decent cost to
weight ratio. However, the group was disappointed since we were expecting it to
hold more than 35- 40 lb. Testing our bridge serves as a major accomplishment
since we were able to see the failure points of our bridge. This design, like
most others, failed at the joints. None of the parts actually broke, but the
joints gave up due to the force and separated which caused our bridge to
collapse. Next week we plan to make improvements and changes to our design for
the next one which will be spanning 3 feet.
WPBD readily provided us with the tension/compression
forces acting on each individual parts of the bridge which served as a big
advantage. It allowed us to decide which parts should be compromised in terms
of the material used to reduce the cost. Knowing the forces acting on each part,
specifically gusset plates would allow us to design a stronger bridge. Gusset
plates seemed to be the most common cause of bridge failure, whether it be
through physical breaking of the part or through the separation of joints. The
members seem to be very strong and don’t usually break. So knowing the amount
of force acting on each part would tell us which portions of the bridge are
most crucial. This would allow us to decide upon the type of joints we can use
for different parts of the bridge.
Week 5
During the fifth week we worked on our group bridge
design. We started with three individual designs, and went with the one which
seemed the strongest. We tried adding and subtracting minor, different
variations to that design until we settled upon one. We tested our bridge in
class so we can notice the weak points and try to improve on those areas for
our final group design that we turn in for the competition. Major
accomplishment for this week is that we have the general idea for the design of
our bridge. Our plan for next week is to build the final Knex bridge that will
be turned in to compete against other bridges. We did not finish calculating
the cost of our bridge so that’s a task for next week as well. We are standing
at a good position right now, and don’t have any issues.
My view on the similarities and differences between WPBD
and Knex hasn’t changed much at all. Knex only provides us with one material
for the bridge, but has different lengths and gusset plates. A couple of things would have different
considerations if we were to compare the Knex bridge model with a real steel
bridge spanning 20’. For the real bridge, we would have options for using
different materials for the chords and the web members based on the amount of
force/load each has to bare. Knex, as mentioned above, only provides us with
one type of material. We would also have stronger joints at the gusset plates
in the real bridge since we would be able to weld it in place. On the other
hand, Knex connections are really “welded”/ held together properly, which is a
main reason for the Knex bridge to collapse. The chord pieces in Knex don’t usually
break, proving that they’re able to withstand a lot of force before they break
at the joints. We would also need to build a base for the real world bridge
whereas we don’t build one for the Knex model.
Week 4
During the fourth week we had a presentation on the
Knex bridge assignment which laid out the goals and objectives in detail. It
objective is to have the cheapest bridge and possible which can withhold the
maximum weight. So our goal is to reach the lowest numbers possible when the
cost of the bridge is divided by the weight it holds at the failure point. The
price for each Knex parts was laid out in the presentation as well. We also had
a brief presentation from Mr. Jay Bhatt who introduced us to engineering
specific database and sources. The remaining time was spent familiarizing
ourselves with the Knex kit, which can be considered as one of our major
accomplishments since we will be using them for the rest of this term. Next
week, we will be building our individual bridges based on the design that we
proposed. There are no major issues that we face right now. However, I don’t have
any past experiences with Knex and as a result the bridge I built in class
failed at the joints upon applying pressure. So part of my challenge is to
experiment with different joints until I reach a sturdy one.
As we move from WPBD to Knex, I can point out some
similarities and some differences between the two. They’re both limiting in the
variety of ‘material’ they provide us to use for the bridge. Also they both let
us built and analyze the bridge but they do not include the labor cost. This is
a crucial component since our overall goal, in both the cases, is to have the
lowest cost. One major difference between the two is that WPBD exaggerates the
weak points of the bridge in the animation and also calculates the different
forces acting on different parts of the bridge, allowing us perform several
tries on the computer until we reach a functioning model. Knex model on the
other hand is physically tested and it does not provide us with electronically
computed data. We would have to compute the forces ourselves and rebuild
different designs to reach a better result. In WPBD our goal was to design the cheapest bridge possible which is capable of moving the truck
across; thus the weight load had a limit. With the Knex model, we have to
design the cheapest bridge that can support the maximum load until its failure
point.
Week 3
During the third week, the class had a brief discussion about the different factors that would be considered during the construction of a bridge. For example, the cost of the bridge wouldn’t be the only thing that people would care about. Other factors like the life span, weight holding capacity and the look of the bridge also come into consideration. We also reviewed the comp1 results where the costs of everyone’s bridges were compared with the depths. We further saw the design and animation of the cheapest bridge, priced at about $222k. The rest of the class period was spent collaborating with our group to combine our ideas in order to build a better bridge. We followed our initial arc design and did not take symmetry/ looks of the bridge into account since our goal was to design the cheapest bridge possible. We managed to design a functioning bridge at a cost of $221k which is one of our major accomplishments for this week. Next week we plan to further work on our bridge to reduce the cost. We have also prepared some bridge specific questions to ask Mr. Bhatt during his visit next week. Currently, there are no issues that we face individually or as a team.
After using the West Point Bridge Design program for a couple of weeks, we can point out the realistic and non-realistic features of the program. In real world, designing is an open-ended process in which one can alter their designs multiple times in order to achieve a better result. The real world also has specific conditions and restrictions, which is demonstrated by WPBD by limiting our span lengths and the limited variety of materials available. WPBD conducts standard load tests and calculates the compression and tension forces as specified by AASHTO, the standards which govern the design of highway bridges in US. These features allow WPBD to be considered realistic. However, there are a few things not considered in WPBD which would greatly be affected in real world.
The cost in WPBD doesn’t accurately reflect labor cost etc. which would offset the budget in real world. WPBD also does not consider fatigue- the tendency of a structural material to fail prematurely. WPBD allows and displays the deflection of the bridge and lets us compromise the bright strength with the cost. In real world, the deflection and bridge strength are a major criterion as we take the safety into account. While conducting the load test, WPBD moves the truck in one direction and does not have more than one vehicle on the bridge simultaneously. This allows us to have a functioning asymmetrical design. In real world, though, traffic would be moving in both the directions, and would have multiple vehicles travelling on the bridge. Along with the live load, real world bridges would also have to withstand rain, snow and other forces caused by external objects which are not considered in WPBD. All in all, WPBD is a good tool to gain basic knowledge about bridges, but we should consider the face that non-realistic features outweigh the realistic features in the program.
Week 2
During the second week, we were shown a PowerPoint presentation with a few different types of bridges that had truss designs in them. We also viewed video clips of two fatal bridge collapses and learned more about the bridges along with some vocabulary. We utilized the remaining time in familiarizing ourselves with the West Point Bridge Design software by designing a bridge. For the next week, our group will be evaluating each other
individual bridge designs and combining different ideas to design the final bridge.
Major accomplishments from the second week include the installment of WPBD on my personal laptop as well as acquiring the basic knowledge of utilizing it to design our bridges. I learned some different features about the software during the process of designing my own bridge which include but are not limited to the different types of steel beams we can use, the thickness of each member, different viewing angles of the animation etc. There are not any issues that we face right now.
Some potential questions that I can ask Mr. Bhatt during his visit to our class include:
- Would I be able to find a book or a collection of bridges that have failed to perform well? This can help us explore the specific faults that caused the failure and keep us from using a design like that for our bridge.
- What would be a good resource that would provide us with visual data (pictures, blueprints etc.) on famous truss bridge designs?
- Is there a source that would let us input the basic information of our bridge design and help us calculate the force/ load on different parts of the bridge?
Week 1
During the first week of ENGR-103, most of the class time was taken to explain the course goals and objectives. In the remaining time we divided into groups of 3 people who will be working as a team for the bridge design module. We introduced ourselves to each other, exchanged contact information and filled out the group information sheet. In the coming week, we plan to conduct some research on different types of bridges so we can enhance our knowledge and incorporate those ideas in our own bridge design. For example we can see how an arc shape can be integrated with a truss design. Our major accomplishment from week 1 is the setup of our blog which is a major component for this course. There aren’t any major issues that we face at this point since it has only been one week and we haven’t gotten deep into the project components yet. The first week’s reading focuses on teamwork which is not only a part of this course, but almost all the engineering fields. With multiple people in a group, there may be a few problems that may arise in the future. For example, not everyone’s thoughts and opinions are always going to be the same when making a decision. In which case, we plan to give everyone a chance to explain their opinion and listen to them from their point of view, and then make our decision based on the facts presented. One of the other problems might come up when deciding on a group meeting time. Since everyone would have different schedules, and me being a commuter, it would be hard to decide on a time that is convenient for everyone. In that case we would have to compromise and work our way around the busy schedule.
No comments:
Post a Comment